I-90 in Downtown Cleveland Reopens More Than 32 Hours Early, and Cedar Avenue Bridge Is Closed for Good

A weekend shutdown of I-90 through downtown Cleveland ended early: the Ohio Department of Transportation says crews reopened the interstate Saturday night, more than 32 hours ahead of schedule, after bridge work tied to a $328 million interchange rebuild.
Get Big Rig Daily every morning
The trucking stories drivers are talking about, in one short email. Unsubscribe any time.
After you sign up, check your inbox for an email from news@bigrigdaily.com and tap the button to confirm.
Quick answer
ODOT District 12 said in a social media post that I-90 in downtown Cleveland reopened Saturday night, Nov. 21, after a full closure in both directions near Carnegie Avenue for work on the East 22nd Street and Cedar Avenue bridges, Cleveland19 reported. The early finish put crews more than 32 hours ahead of schedule. According to ODOT's project fact sheet, the Cedar Avenue bridge over I-90 will be permanently removed, and the East 22nd Street bridge is among those being replaced.
Key facts
- Reopened: Saturday night, Nov. 21, 2026, more than 32 hours early (ODOT District 12, via Cleveland19)
- Work: East 22nd Street and Cedar Avenue bridges over I-90
- Cedar Avenue bridge: permanently removed (ODOT fact sheet)
- East 22nd Street bridge: being rebuilt, to be reconstructed and reopen next year (Cleveland19)
- Project: I-90 Central Interchange, between East 9th Street and Carnegie Avenue
- Cost and contractor: $328 million bid, Kenmore Construction of Akron (ODOT fact sheet)
- Completion: summer 2032 (ODOT fact sheet)
What else changes
ODOT's fact sheet says the project replaces pavement on I-90 between East 9th Street and Carnegie Avenue and replaces multiple bridges, including the I-90 west to I-77 south ramp, I-90 over East 14th Street and ramps to I-77 south, and East 22nd Street and Carnegie Avenue over I-90. Community College Avenue will be permanently closed between East 14th and East 22nd streets. ODOT posts closures for Cuyahoga County projects at transportation.ohio.gov/cletraffic.
Get Big Rig Daily every morning
The trucking stories drivers are talking about, in one short email. Unsubscribe any time.
After you sign up, check your inbox for an email from news@bigrigdaily.com and tap the button to confirm.
Who it affects
Trucks moving through downtown Cleveland on I-90, I-77 and the Innerbelt should expect more closures through 2032. Local routes that used the Cedar Avenue bridge will need another way across. Big Rig Daily's hours of service break calculator helps plan around delays like these.
Analysis
The early reopening is ODOT District 12's own report, and the long-term changes are in ODOT's fact sheet: a $328 million project running to summer 2032, with the Cedar Avenue bridge gone for good. More weekend closures are likely before it is done.
How much does an early reopening change your trust in a posted closure schedule?
Save this story for later

Sources
Get Big Rig Daily every morning
The trucking stories drivers are talking about, in one short email. Unsubscribe any time.
After you sign up, check your inbox for an email from news@bigrigdaily.com and tap the button to confirm.